Taiwan Highspeed Rail

  • Taiwan Highspeed Rail

At the beginning of this millennium, if you wanted to travel from the northern Taipeh, capital city of Taiwan, to Kaohsiung, the islands’ industrial center in the south, you had to allow for a very long travelling time. Hence, in the year 2000, construction works started on the High-speed Railway Line to connect these two cities on the west coast.

At that time this railway project was listed as the largest infrastructure project in the world. This major construction project was divided into 12 lots; and HOCHTIEF Construction AG was involved in a joint venture to design and build a segment of approx. 40 kilometers length (Lot C 250); located close to the city of Taichung.

The ambitious task was to complete the project within only 50 months, including all the different types of segments, such as concrete bridges, steel bridges and tunnels in a partly densely populated area and of high earthquake risk. Roughly 90% of lot C250 had to be built as viaducts.

Since the completion of the projects in 2005, the designated journey of 350 kilometers, takes only 90 minutes. At a maximum speed of 350 km/h, the Japanese rival of the German ICE, the Shinkansen, carries approx. 300.000 passengers a day.

 

Facts and Figures:

  • Track length: total 350 km, segment Los C250 about 40 km
  • Construction period: 2000 - 2004
  • Total investment: approx. 15.9 billion EURO
  • Contract value: approx. 730 million EURO
  • Personnel: At its peak about 2600 workers & employees on site

 

 

Contact

Alexander Strutzke
Alexander Strutzke
Dipl.-Geogr.
Dipl.-Betriebswirt (FH)
Sales and Marketing Manager
phone: +49 (931) 35503-550

Successful project collaboration with EPLASS:

This major project marks an important early milestone for the development of EPLASS. HOCHTIEF partners from India, Taiwan and the Great Britain were allotted in the system to create the drawing files. The reviewing process was made simultaneously from locations in Taichung, Essen and Copenhagen. All partners shared EPLASS as their concerted project platform.

At the beginning of this project, the existing Internet bandwidth presented a challenge to the IT infrastructure. Since EPLASS can be operated in parallel as a local installation (on-premise) and on the Internet, it was the ideal solution for this large organizational task. Via the automatic data synchronization of EPLASS (so-called replication) the current data was always available for all locations at the same time.

The use of EPLASS in this project demonstrated in practice, that a worldwide design and construction of a building project can be made technically- & cost-efficient via the internet. The 7 hours time difference between Taiwan and Europe allowed for an effective work period. Change requests from the construction site in Taiwan were entered in EPLASS in the morning via the integrated redlining function, and were implemented on the same day by the responsible party in India or Europe.